Главная Строительство Micron Pushes Start of $100B New York Megafab to 2026

Micron Pushes Start of $100B New York Megafab to 2026

от admin

Revised schedule says first production plant now will operate in 2030

After nearly two years of schedule drift, environmental filings confirm that Micron Technology now plans to begin construction in mid-2026 on the first fabrication plant of its planned $100-billion semiconductor manufacturing complex in Clay, N.Y., north of Syracuse.

The final Environmental Impact Statement for the project, filed with the Onondaga County Industrial Development Agency, revises the project timeline and pushes the first plant’s operating date to 2030.

During a Nov. 6 public hearing on the filing, County Executive Ryan McMahon called the plan “a truly monumental and tangible step forward” and acknowledged the long delay from its originally targeted 2024 start.

“[This is] the worst-case-scenario timeline … not a reflection on anything other than the construction schedule of what it takes to build this,” McMahon said, according to local TV coverage of the meeting.

Infrastructure Realignment

The later start reshapes schedules for contractors and engineers involved in the project’s technically demanding and infrastructure-intensive industrial builds. The New York State Public Service Commission in October approved a two-mile, 345-kV underground transmission line linking the existing Clay substation to the Micron campus—a key utility milestone. 

RELATED

New York Greenlights Power Link for Micron’s $100B Megafab

New York Gov. Kathy Hochul, recognizing the urgency in achieving project-ready status, said previously that the state “is moving quickly ahead with all due speed and deliberation.” Heavy-industrial contractors note that prolonged preconstruction periods heighten exposure to inflation and complicate workforce planning.

Читать также:
Sickened Employees at Kimley-Horn Lead to Multimillion Dollar Rent Dispute

Dig Deeper:

Micron Technologies | Final Environmental Impact Statement (Full Text)

New York’s Green CHIPS incentive program—offering up to $5.5 billion in credits tied to verified job creation and capital milestones—remains in place but will track the revised schedule. Federal CHIPS Act funds administered through the U.S. Commerce Dept. are also contingent on construction progress.

The final project environmental review «reflects years of collaboration and diligence,” said Rob Simpson, president of CenterState CEO, a Syracuse-based business alliance in a statement. “At the same time, we want to underscore the need for timeliness and momentum. Our region and our country need this project to come online as soon as possible to ensure our national security and economic competitiveness.”

Industry analysts suggest the delay could exceed the two-year slip cited in public filings. TrendForce reported Nov. 10 that Micron’s second plant may not open until late 2033, while Digitimes Asia said some CHIPS Act funding may be redirected to Micron’s Idaho facility. 

A Nov. 10 Tom’s Hardware summary echoed those findings, citing internal sources that forecast a multi-year re-phasing of Micron’s U.S. manufacturing program. Locally, CNY Central reported community unease over the revised schedule and the project’s 49-year property-tax agreement with Onondaga County.

RELATED

Micron Projects in New York and Idaho Set for $6.1B in Federal Funding

County officials said site clearing and utility corridor work will continue through the end of 2025, ahead of major construction mobilization in 2026. ENR was unable to reach Micron regarding reports of timelines extending beyond the 2030 target.

Micron’s four-plant campus—covering 1,377 acres and projected to create more than 50,000 jobs, including about 9,000 direct Micron positions, according to the governor’s office—remains central to the federal drive to expand domestic semiconductor manufacturing. 

Company and state officials have said the site could produce roughly one-quarter of all U.S.-made semiconductors by 2030.

Вам также может понравиться

о нас

Блог о машиностроении и технике.

Актуальные ежедневные новости, касающиеся машиностроения, транспорта, техники, авиации, космоса и всех отраслей, связанные с этой тематикой. Аналитические интересные статьи от наших корреспондентов!

Блог о машиностроении и технике | PCL Construction Will Build B Natural Gas Plant in North Dakota

ВЫБОР РЕДАКТОРА

@2024 — Promvestnik.ru. Все права защищены.

Блог о машиностроении и технике